General Site Maintenance for the WWTP Expansion Project, Lilly

Villavicencio & Associates was selected to install and maintain on a daily basis all Stormwater BMPs of Eli Lilly WWTP Expansion Project. V&A personnel where trained to comply with all requirements by Federal and local authorities. In addition to Stormwater BMPs accountability, Villavicencio & Associates at hand with Fluor management did all the setout works for future construction of the WWTP expansion. This consisted in selective and structure demolitions, surveying services, exploratory hydro-excavations, existing tank rehabilitations and finish works. After all setout works were carried out, Villavicencio & Associates personnel remained on site for stormwater BMPs maintenance and general site maintenance including construction debris management, recycling management and facilities maintenance.

Contract Amount: $1,088,474
Completed: January 2015