Architectural & Concrete Works
|
Green Building considerations: |
The scope of work of this project included the construction of three free standing concrete towers up to 80 feet high. The architectural aspect of the project included: special flooring, concrete, block and gypsum walls, and acoustical, gypsum, and metal ceilings; first facility in Puerto Rico for parental process. The construction of the Central utility building for new parental process building was also part of the project.
Contract Amount: $7,938,500.00
Completed: December 2011
|
- Construction Activity Pollution Prevention plan was required and activities were performed accordingly.
- Site Development, the project considered the protection and restorations of the surrounding habitat.
- Low-Emitting materials, adhesives & sealants, paints & coatings were installed.
|
|
|